Scheduler
Scheduler is displayed only if the HULFT10 Server grade is installed.
- Weekly Non-working Days (weekoff)
-
Specify days of the week for non-working days. You can specify up to three days of the week.
If you do not want to specify any day as a non-working day, clear the check boxes.
- Include Holidays in Non-working Days (holiday)
-
Specify whether or not to set holidays as non-working days.
- Scheduling Time (schtime)
-
Specify the time when HULFT Scheduler carries out scheduling, in hours.
Set a value from '0' to '23' in 24-hour format.
= Remarks =Once a day at a specified time, HULFT Scheduler carries out scheduling. During scheduling, Scheduler checks the information that the user has specified and prepares the execution of jobs that are scheduled to be executed within 24 hours from the time of scheduling, as the jobs for the day.
- Schedule Process Multiplex Level (schnum)
-
Specify the number of jobs that can be executed at a time. Set a value from '1' to '999.'
- Designated Non-working days
-
You can specify special non-working days other than standard non-working days and holidays. When you click the Calendar button, you can select a date. To add the selected date to the list, click Add. To delete a date from the list, select the date that you want to delete, and then click Delete.
= Remarks =If a designated non-working day is the same day as a holiday, the day is processed as the designated non-working day. Therefore, even if you clear the Include Holidays in Non-working Days check box, the day is processed as a holiday.
- Holidays
-
Specify holidays. When you click the Calendar button, you can select a date. To add the selected date to the list, click Add. To delete a date from the list, select the date that you want to delete, and then click Delete.